Hello Guest it is March 28, 2024, 11:14:51 AM

Author Topic: GO TO ZERO question  (Read 3014 times)

0 Members and 1 Guest are viewing this topic.

Offline Garyv

*
  •  103 103
    • View Profile
GO TO ZERO question
« on: July 18, 2009, 10:26:38 PM »
How do I get the Z axis to come to clearance BEFORE X and Y move to Zero position without manually lifting the tool to clearance before hitting the go to Zero Button?
Is there a script or macro I can change for that? ???
Thanks
Gary
Re: GO TO ZERO question
« Reply #1 on: July 18, 2009, 10:32:03 PM »
Go to Config->SafeZ Setup
Regards,
Ray L.

Offline Garyv

*
  •  103 103
    • View Profile
Re: GO TO ZERO question
« Reply #2 on: July 18, 2009, 10:42:18 PM »
Thanks Himmy,
   I knew it was something stupid.. I had everythign running great then had a computer crash lost all XML files and forgot about that one ..Just changed it works like a charm.. ;D
THanks
Gary
« Last Edit: July 18, 2009, 10:46:10 PM by Garyv »