1
General Mach Discussion / Mach3 cant reach desired position .00x
« on: May 16, 2014, 04:51:19 AM »
I have a rotary axis as x. normally i use steps per unit as 200 and velocity as 120. I have calculated a full rotation on x axis exact value of x12.6 and my 90 degree rotation is x3.15,
On another machine i was able to make a different reduction.
I made
Steps per: 195.4 and velocity: 36
Then i calculated an absolute rotation as X6.407,
after that when i try to send x axis to 6.407 i saw that is going somewhere else like x6.38,
I tried to change values like making steps per:1.954 and velocity:3600
In this calculation my full rotation was x640.7
i can get x640.7 on full rotation but my 90 degree rotation was x160.175 and i could'nt get exact value. it went x160.08 and measurements were wrong on table.
Any suggestions for this situation ?
On another machine i was able to make a different reduction.
I made
Steps per: 195.4 and velocity: 36
Then i calculated an absolute rotation as X6.407,
after that when i try to send x axis to 6.407 i saw that is going somewhere else like x6.38,
I tried to change values like making steps per:1.954 and velocity:3600
In this calculation my full rotation was x640.7
i can get x640.7 on full rotation but my 90 degree rotation was x160.175 and i could'nt get exact value. it went x160.08 and measurements were wrong on table.
Any suggestions for this situation ?